Are you after long term monitoring, or point in time?
Clamp ammeters may be of assistance in determining load at a given time,
but they cant be relied upon for high accuracy. They do meet your
requirement to not power stuff down though.
Frankly, I am surprised that sub-metering at the load side (ie close to the
rack) isn't done more frequently in data centres, as this would allow
accurate metering and easily sharable data to prove/disprove power
consumption claims.
On 04/06/2013 7:15 PM, "Alastair Waddell" <awaddell at legion.com.au> wrote:
> Hi All,
>
> Warning: much ignorance about all things power related.
>
> I'm wondering if I can commission a power audit of a rack-load of gear.
>
> Who might provide such a service?
> Can it be done without powering down?
>
> ie Power person attaches something around each AC cord and reports amps
> drawn. The sum should approximate what my provider bills which would
> address concern #1 and the individual results should let me identify any
> miscreant device which would address concern #2
>
>
>
> Regards,
> --
> Alastair Waddell
> Legion Internet
> Australia
>
> _______________________________________________
> AusNOG mailing list
> AusNOG at lists.ausnog.net
> http://lists.ausnog.net/mailman/listinfo/ausnog
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.ausnog.net/pipermail/ausnog/attachments/20130604/6a6de5f9/attachment.html>
More information about the AusNOG
mailing list