[AusNOG] Brisbane Datacentre Question

Jon Eaves Jon.Eaves at dedicatedservers.net.au
Tue Jan 10 14:38:50 EST 2012


 

DedicatedServers did not lose power during the floods at either Milton
or the old site at 20 Wharf. Neither did either of the buildings.

 

 

 

From: ausnog-bounces at lists.ausnog.net
[mailto:ausnog-bounces at lists.ausnog.net] On Behalf Of Craig Askings
Sent: Monday, 9 January 2012 9:34 AM
To: ausnog at lists.ausnog.net
Subject: Re: [AusNOG] Brisbane Datacentre Question

 


Ones I believe stayed up [FYI edits in brackets]

- The DC that was in the 20 wharf st at the time (now NextDC's B1)
[Maintained Energex/mains Power]
-  Dedicated servers DC in Milton [Lost Energex/mains Power]

 

[b]



 

The information contained in this email and any attachments may be
confidential. This email and any attachments are also subject to
copyright. No part of them may be reproduced, adapted or transmitted
without the written permission of the copyright owner. If you are not
the intended recipient, any use, interference with, disclosure or
copying of this information is unauthorised and prohibited. If you have
received this email in error, please immediately advise the sender by
return email and delete the message from your system. All email
communications to and from NEXTDC Limited are recorded for the purposes
of archival and storage. 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.ausnog.net/pipermail/ausnog/attachments/20120110/603809c8/attachment.html>


More information about the AusNOG mailing list