You would think that given
> One of the emergency diesel generators failed to start due to a
> synchronization processor failure.
They might not say the following
> The upgrade of the CitiPower substation that is planned for this
> coming
> weekend, will continue as previously advised.
And that they might wait until the gens can be guaranteed to start and
sync properly.
Or perhaps I dont appreciate the logistics behind the work that is
happening next weekend. :-)