[AusNOG] From the AGD - Data Retention - Starts October 15 2015
Peter Fern
ausnog at 0xc0dedbad.com
Mon Jul 20 09:20:11 EST 2015
On 07/20/2015 08:51, Joseph Goldman wrote:
> Hi *,
>
> Looking over the AGD's website, I can no longer find reference to
> when the Implementation Plan has to be submitted by. I recall early
> documents suggesting the plan itself must be in by 13th August 2015,
> but the only date relevant now I can find is 13th October 2015, which
> is where you must start collecting data if you do not have an approved
> implementation plan.
>
> I'll obviously email off to the CAC as well, but just wondering if
> anyone can link to specifically where it says the implementation plan
> must be submitted?
It's in one of the PDFs they'll send you. Submitted plans must be
reviewed within two months by the AGD, so you need to have your plan in
two months before retention starts so that they can be reviewed within
the legislated time frame, hence 13th Aug.