[AusNOG] Process for installing new kit in existing racks in .au data centres?

Warren Bold wbold at polyfone.com.au
Tue Mar 25 11:16:09 EST 2014


I just organised some kit to be sent to an Equinix DC today and they did not ask for any serial numbers. So it looks like AU Equinix are more relaxed.

We do have to give power requirements and serial number to some of our non Equinix DCs. 

Kind regards

Warren Bold


-----Original Message-----
From: AusNOG [mailto:ausnog-bounces at lists.ausnog.net] On Behalf Of Mark Newton
Sent: Tuesday, 25 March 2014 9:49 AM
To: Robert Hudson
Cc: ausnog at lists.ausnog.net
Subject: Re: [AusNOG] Process for installing new kit in existing racks in .au data centres?


On 24 Mar 2014, at 4:17 pm, Robert Hudson <hudrob at gmail.com> wrote:

> I'll echo the responses so far - even with "average" data centre operators, once on the approved access list, I rock up with whatever I want, and install it into the rack I'm paying for as I see fit.  If I need dock access, I'll let them know in advance.

Equinix IBXs in the US want asset numbers or serial numbers of installed kit. Their security folks also require an authorized person to cite the asset number or serial number of each item that is removed from the facility.

I can't remember if they work the same way in Australia.

   - mark


_______________________________________________
AusNOG mailing list
AusNOG at lists.ausnog.net
http://lists.ausnog.net/mailman/listinfo/ausnog