[AusNOG] Power audit

Adam Gardner Adam.Gardner at vocus.com.au
Wed Jun 5 09:53:17 EST 2013


In terms of non-intrusive retroactive measurements without powering down
the equipment or replacing power rails etc, this solution may work for you.

http://www.unitetechnologies.com/products/power-monitoring-and-control/cl-a
mp.aspx

http://www.unitetechnologies.com/media/19003/cl-amp.pdf

We have not yet utilised these, but may be a good way if you definitely
can't power down your kit.

I'd be surprised if any colo facility would remove the protective cover to
expose the active wire on live equipment for OHS and the risk involved.

Kind Regards
 
Adam Gardner | GM Operations ­ Vocus Data Centres
 
M: +61 433 955 399   D: +61 8 9216 6623   E: adam.gardner at vocus.com.au
P: 1300 855 845 or +61 2 8999 8999   W: http://vocus.com.au
<http://vocus.com.au/> A: G, 1 William Street, Perth WA 6000
 





On 5/06/13 12:44 AM, "Matt Perkins" <matt at spectrum.com.au> wrote:

>Well yes and no. If you are in a data center and have no authority over
>the power supply cabling and switch boards etc. that is renting colo.
>It's likely a no as in the colo providor will understandably not grant
>access to the switch boards cabling etc to get estimates of the current
>draw from your rack.  As others have said you can "tong" but also
>unlikely because the cable to your rack likely has active and neutral in
>one multi core cable so to tong you need to put the meter around just the
>active or just the neutral. you can't do that because both are in one
>cable these will cancel each other out if you put the meter around both.
>
>you can do the doggy pull apart live and try to snag a active with the
>tong but no insurance company, big electrically company or person without
> gusto will do that.  and perhaps they should not any way
>
>so if you have some sort of power board that already meters usage then
>I'm guessing you would not be asking so.
>
> I started with yes and no let me just change that to no.
>
>look at the usage for the power supply's for the equipment in the rack
>and estimate. other then  that your stuffed without and outage.
>
>
>
>excuse the phone with incorrect punctuation / formatting but at least
>that elect. eng.has final been used for something :)
>
>Matt
>
>
>On 04/06/2013, at 6:42 PM, Alastair Waddell <awaddell at legion.com.au>
>wrote:
>
>> Hi All,
>> 
>> Warning: much ignorance about all things power related.
>> 
>> I'm wondering if I can commission a power audit of a rack-load of gear.
>> 
>> Who might provide such a service?
>> Can it be done without powering down?
>> 
>> ie Power person attaches something around each AC cord and reports amps
>>drawn. The sum should approximate what my provider bills which would
>>address concern #1 and the individual results should let me identify any
>>miscreant device which would address concern #2
>> 
>> 
>> 
>> Regards,
>> -- 
>> Alastair Waddell
>> Legion Internet
>> Australia
>> 
>> _______________________________________________
>> AusNOG mailing list
>> AusNOG at lists.ausnog.net
>> http://lists.ausnog.net/mailman/listinfo/ausnog
>_______________________________________________
>AusNOG mailing list
>AusNOG at lists.ausnog.net
>http://lists.ausnog.net/mailman/listinfo/ausnog